Lots of people are really interested in the new Watauga High School.
Here’s some facts:
- The town has set a price tag of $60 Million
- The groundbreaking began September 20, 2007
- The town will borrow $70 Million Read More
- The school will be 274,000 sqft
- the new campus is 94 acres (20 more than current site)
- the estimated traffic flow is 40% west and 60% east
- Students that live outside watauga county will pay tuition Read More
- There will be 972 parking spaces.
- The project is scheduled for completion spring of 2010
- Classes begin fall 2010
Click here to see exactly where the campus will be via Google maps
Click here for a blog dedicated to the new highschool
Update: Concrete being poured 4/13/08
Watauga High School road expansion
The DOT is planning to remove the row of shops on the Dan’l Boone Inn corner, to allow a new right turn lane.
According to the Uniform Relocation Act, tenants will be eligible to collect up to $10,000 in reestablishment expenses, up to $2,500 in search expenses and will also be reimbursed for any and all moving costs. Tenants could also choose to settle for a single, one-time payout of $20,000 to cover all moving and reestablishment expenses.
Here’s the High Country Press article
Watauga County May Borrow $70 million for New High School
The resolution notes the county doesn’t expect property tax increases to repay the loan, since it is selling the current high school property. The construction price for facilities is set at a guaranteed maximum of $47.2 million, with another $11.2 million committed in land purchases, site testing, studies and design work. A public hearing on the proposal is scheduled for the next regular meeting at 6 p.m. on Feb. 19.
Click here for the Mountain times article